Friday, 14 August 2020 / Published in Northwest Idea House 2021

2021 NW Idea House: Update #4

August 14, 2020 / Admin
Pictured: Todd Lozier oversees his team’s good work at the NW Idea House.

Things are going smoothly here at the Idea House! As we work to start framing, we must first attend to the tremendous amount of preparation work on the basement slab.

Here, we backfilled the interior with free draining compactible fill.
The next step consisted of the installation of the plumbing drains, which were embedded in sand and inspected below grade.
We then backfilled the plumbing trenches and water settled the backfill with sprinklers.
Then, we installed electrical conduits under slab (floor outlets), applied 8 mil vapor barrier and fully insulated with R-10 rigid insulation (except at bearing points).
Here, we installed a pressure treated 3×12 plate and spray foam insulation underside for thermal break.
Finally, we installed 6×6 wire mesh and red radiant tubing.  Everything got inspected by the County and then we were ready to pour 4-1/2” of concrete throughout.
Tagged under: 2021 NW Idea House, basement slab, environmentally friendly, Lochwood-Lozier

What you can read next

2021 NW IDEA HOUSE UPDATE #21
2021 NW IDEA HOUSE UPDATE #20
2021 NW IDEA HOUSE UPDATE #19

© 2025 Lochwood-Lozier Custom Homes, Remodeling and Landscaping
Site by Motive

© 2025 Lochwood-Lozier Custom Homes, Remodeling and Landscaping | Site by Motive

TOP